Sean Simonson, from the City of Northfield’s Engineering Department, sent me an update on the Library Plaza Project:

The contractor will begin construction on the Third Street crosswalk on Monday July 31, 2006. Therefore they will be closing Third Street from Washington Street to Division Street. The Contractor has 10 working days to complete this work. Barring any delays, they should have Third Street back open on Friday August 11, 2006. Please feel free to contact me with any questions regarding the Library Corner construction.

Having this work completed will be good news for businesses and customers on the north end of Division.